In mid-March the wall from the present building to the connecting corridor to the extension was broken through on the street-level. The new Quiet Room is now accessible from the main concourse of the meeting house.

Start of the removal of the wall next to the main meeting room

Meanwhile work continued in the new parts of the building. Windows have been fitted to the linking corridor, the Quiet Room and the garden room as these photos from Chris Edwards show:

Inside the new Garden Room


View of the new link corridor from the terrace. The Quiet Room is on the left.

The new Garden Room and the Quiet Room (upper floor)


Inside the Quiet Room, work began on installing the ceiling:




In the meantime, outdoors, Chris Edwards (Meeting House Manager) and David Peryer (Treasurer) continued their hands-on approach to the project by dealing with work in the garden, and with the removal of a tree: